Diversion tunnels have been completed to redirect the Peace River during low water this summer and fall, in one of the most critical steps to completing the Site C dam, March 2020. (BC Hydro)

B.C. Hydro’s Site C set back by COVID-19, foundation changes

Peace River diversion still on track for this fall

B.C. Hydro’s plan to have the third dam on the Peace River complete and in service by 2024 has been set back by work scaling down due to COVID-19 restrictions on construction projects, and additional foundation strengthening for the powerhouse and spillway.

In a progress report filed with the B.C. Utilities Commission July 31, B.C. Hydro CEO Chris O’Riley says the Site C project is still on track to divert the Peace River through a pair of tunnels and begin in-river work. But that too has been complicated by geological conditions. The financial impact of the coronavirus delays and additional work will be better known in the fall, O’Riley said.

“Pandemic-related delays will present further cost pressure on the budget,” O’Riley wrote in a letter to BCUC chair David Morton. “As the evolution of the pandemic is uncertain and the date of resolution is unknown, various cost and scheduled impact scenarios continue to be assessed and refined as part of the re-baselining process.”

The incoming NDP government reluctantly decided to carry on with Site C, after former premier Christy Clark vowed to push the project “past the point of no return” before the 2017 B.C. election. In doing so, Premier John Horgan approved an updated cost estimate of $10.7 billion to complete it, an increase of about $1 billion from the initial estimate.

RELATED: Site C dam project carries on under NDP government

RELATED: NDP pays off $1.1B in B.C. Hydro debt, seeks rate cut

RELATED: After losing at every level, West Moberly sues again

Now the combined effects of COVID-19 and a series of problems have pushed the cost up by an amount not yet known. Those issues included changes to the main civil works contract, increased costs of reservoir clearing, power line construction and highway realignment, and first nations treaty infringement claims and an injunction application.

“Towards the end of December 2019, investigations and analysis of geological mapping and monitoring activities completed during construction identified that some foundation enhancements would be required to increase the stability below the powerhouse, spillway and future dam core areas,” O’Riley wrote.

Before the COVID-19 pandemic, Site C was on track for completion by fall 2023 and full service to the B.C. Hydro grid by 2024.


@tomfletcherbc
tfletcher@blackpress.ca

Like us on Facebook and follow us on Twitter.

BC legislatureCoronavirusSite C

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

Vanderhoof sees a surge of scam callers

Residents have received multiple unknown phone calls from a person claiming to be a representative of the CRA or law enforcement, local mounties said.

Brucejack mine fatality identified

Patrick Critch was from Newfoundland

Pretivm Resources reports fatality at Brucejack mine

The isolated incident occurred last Friday, and the employee passed away on Sunday in hospital

QUIZ: How much do you know about British Columbia?

On this B.C. Day long weekend, put your knowledge of our province to the test

Smoke seen over northern B.C. from wildfires in the U.S. and Siberia

Smoke was seen over Vanderhoof, Fort St. James and Prince George on Friday, July 31.

B.C. doctors, dentists call on province for mandatory mask rule

Open letter says masks should be worn in indoor public spaces, public transportation or in crowds

Dwindling B.C. bamboo supply leaves Calgary Zoo biologists worried about pandas

Zoo has been trying to send pandas back to China since May

Facebook launches its new TikTok clone, Instagram Reels

Facebook has a long tradition of cloning competitive services

B.C. Appeal Court prevents Victoria woman from using the term ‘death midwife’ in her job

Pashta MaryMoon claimed she had been providing “death-care services” for more than 40 years

‘We all have anxieties’: B.C.’s top doctor addresses return-to-school fears amid COVID-19

Dr. Bonnie Henry promises school restart plan safe for B.C. kids

Abbotsford mom worried about her two kids in Beirut following explosion

Shelley Beyak’s children were abducted by their dad in 2018

Young Canadians, hospitality workers bear the brunt of mental strain in 2020: report

A study by Morneau Shepell points to economic uncertainty in the pandemic as the cause for angst

Health Canada recalling more than 50 hand sanitizers in evolving list

Organization says to stop using products listed, and to consult a health-care professional

Most Read