B.C. pulls plug on power projects

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20

Wind turbine components await construction at independent power project near Chetwynd in 2008. High construction costs stalled B.C.'s first commercial wind energy project

BC Hydro has cancelled or deferred four electricity purchase contracts with independent power producers, and the total may reach 20 by the time a review of projects is complete, Energy Minister Bill Bennett said Thursday.

Bennett said the review is part of a broader effort by BC Hydro to meet his instruction to “spend less money,” as he leads an effort to reduce costs across all government operations.

BC Hydro proposed the move, identifying the 20 project proponents that were not meeting their contract obligations due to financing, regulatory or other problems. That non-performance gives BC Hydro legal authority to delay or terminate contracts.

The utility has contracts with 81 operating projects, mostly run-of-river hydroelectric, and another 47 are under construction or seeking permits after receiving purchase contracts.

BC Hydro released its latest draft resource plan last week, which estimates the province has enough electricity supply to meet growing demand for the next 10 years. Bennett said he is skeptical about that forecast, with population growth and industrial demand from new mines and natural gas development in northern B.C., but it gives the utility some breathing room.

“I’m a real fan of the clean energy industry, but obviously we don’t want to be agreeing to buy more power than what we need,” Bennett said.

BC Hydro has been criticized in recent years for running up billions in deferred debt, as it completes major expansion and seismic upgrading of its network of dams. A new power line to northeast B.C. has run over budget, and the NDP opposition has accused the government of forcing BC Hydro to buy private power at inflated rates through contracts running as long as 40 years.

Bennett said he has asked for a detailed analysis of the cost of private power compared to new sources such as the proposed Site C dam on the Peace River or adding turbines to BC Hydro dams on the Columbia River.

B.C.’s Clean Energy Act requires BC Hydro to be self-sufficient in electricity by 2016, based on an average rainfall year to replenish its hydro dams. The requirement is to minimize the import of power generated by burning coal or natural gas.

Just Posted

Gitdumden checkpoint blocks access to Unist’ot’en camp

Wet’suwet’en clan members say Morice Lake Forest Service Rd checkpoint in effect until further notice.

Column: Windows can be bad news for birds

Dianne Bersea is a member of the South Okanagan Naturalists Club

23-year-old missing from Prince George since Dec. 1

Kari Baxter has a dreamcatcher tattoo on her neck

Passport services expanded to 300 locations across Canada

At Service Canada outlets officers can review applications, validate supporting documents, collect fees and forward applications

Two Vanderhoof students awarded scholarships for post-secondary education

Indigenous students awarded to further their studies

VIDEO: Ex-NASA engineer pranks mail thieves with glitter bomb trap

Package thefts are common this time of year, but YouTuber Mark Rober used his engineering skills

Canadian detained in China, not clear if related to two other detentions

Reports suggest the person is not a diplomat or entrepreneur doing business in China.

Trudeau sees 2019 election as choice between positive Liberals, divisive Tories

Trudeau is drawing much the same battle lines that propelled the Liberals to a come-from-behind victory in 2015

Snowfall warning issued for Coquihalla, Highway 3

Make sure to equip winter tires if travelling

Lightning top Canucks 5-2 in feisty battle

NHL’s No. 1 team too much for Vancouver

FortisBC says you can return to normal gas use following pipeline fire

Utility says increased pipeline capacity, warmer weather have allowed supply to reach normal levels

CSIS collected info on peaceful groups, but only in pursuit of threats: watchdog

Security Intelligence Review Committee says fears unjustified after reviewing evidence, testimony

Canada ranks 16th on annual gender gap list

This is the second year Canada has placed 16th in the World Economic Forum’s list

VIDEO: Tornado rips through city west of Seattle

Reports indicate five to seven homes damaged in Port Orchard, Wash.

Most Read