Coastal GasLink completes right-of-way clearing for first section of pipeline route

The company completed Section 5 — from Vanderhoof to south of Burns Lake — in late March

Sections of pipe for the western most portion of the Coastal GasLink natural gas pipeline have been arriving steadily at a storage yard north of Kitimat. (Coastal GasLink Photo)

Coastal GasLink (CGL) has achieved a major milestone in its 670 kilometre long pipeline set to transport natural gas to its Kitimat facility.

On April 16 the company announced it had completed right-of-way clearing for Section 5 of the pipeline route, from Vanderhoof to south of Burns Lake. The feat was achieved in late March as winter construction wound down in anticipation of the spring thaw.

“This milestone could not have been achieved without the hard work and dedication of all the field personnel who played a role in the execution, and the support of their families, particularly at a time when we have an even greater focus on health and safety as we progress essential project activities,” said Jeff Binda, project manager for Section 5.

READ MORE: Coastal GasLink follows COVID-19 procedures, cuts workforce

The 82-kilometre stretch, along with seven others, are being cleared in advance of mainline pipe installation. Subcontractors NWF Frost and M&M Resources Inc. completed the work.

“We were able to complete this work due to two key factors. First, section 5’s rolling terrain allows for extended stretches of unimpeded work fronts. Second, the work was approached with internal and external collaboration at the forefront,” explained Binda.

He said that this collaboration was key to successful completion of the work.

“The Coastal GasLink team, including the workforce housed at Little Rock Lake Lodge, worked closely with our prime contractor, Macro Spiecapag Joint Venture (MSJV), and our clearing subcontractors to focus on solutions, not problems, so they could continue to gain progress in the field.

“Through problem solving and working together, the route was fully cleared in four months. The team was very motivated by our subcontractors, who set a goal of completing clearing prior to spring break-up, and we did so, always with safety leading the way.”

NWF Frost cleared the east side of the section — approximately 65 per cent of the route — while M&M Resources Inc. cleared the rest of the route to the west. But while the percentages varied, Binda explained in terms of total effort the feat was a 50-50 split, with timber from the east side generally smaller and able to be processed on site versus the larger, sellable timber on the west side which was processed and sent to mills.

An additional challenge for the Section 5 was that it crosses medium and high smoke sensitivity zones, presenting challenges for clearing. Both carry challenges to operate in, with restrictions in the high zone creating the potential to significantly restrict open burning. Additionally, the Open Burning Smoke Control Act, regulation on burning in smoke sensitivity zones, was brought into effect by the B.C. government in December 2019 and prevented burning along the section.

Binda said this provided unique challenges but the company was able to use methods outlined in their environmental management plan to proceed.

“When you have a goal, you just find ways to think outside of the box; we ensured adherence to our environmental commitments and achieved a good balance of cost and schedule considerations while never compromising on safety,” said Binda.

Activity on Section 5 has wound down for spring break-up with the team’s current focus on monitoring the environment on the right-of-way and ensuring there are no sediment control issues.

Binda said in terms of construction, it’s an exciting time.

“Once we begin construction again, we will move to pipeline activities such as grading, grubbing and pipe hauling. We are in the planning stage to ensure we move safely ahead.”



trevor.hewitt@interior-news.com
Like us on Facebook and follow us on Twitter

Coastal GasLink

Get local stories you won't find anywhere else right to your inbox.
Sign up here

Just Posted

July update: 200 workers at CGL pipeline camp in Vanderhoof

District not providing information on total revenue being earned from renting land to TransCanada for CGL camp.

Skeena Resources, Tahltan prez excited by purchase of Eskay Creek

Skeena gets full control of mine, Barrick gets 12 per cent of Skeena and a one per cent royalty

VIA Rail lays off 1,000 unionized workers across the country

Northern B.C. route Jasper to Prince George to Prince Rupert is not affected by VIA Rail layoffs

Man arrested in Vanderhoof in connection to Alberta mall shooting

Jacob Doubt, 23, is facing a number of firearms-related charges

B.C. sees 25 new COVID-19 cases, community exposure tracked

One death, outbreaks remain in two long-term care facilities

VIDEO: Alberta man rescues baby eagle believed to be drowning in East Kootenay lake

Brett Bacon was boating on a lake in Windermere when he spotted the baby eagle struggling in the water

Conservationists raise concerns over state of care for grizzly cubs transferred to B.C. zoo

‘Let them be assessed now before their fate is sealed,’ urges B.C. conservationist Barb Murray

B.C.’s COVID-19 job recovery led by tourism, finance minister says

Okanagan a bright spot for in-province visitor economy

National Kitten Day aka the ‘purrfect’ day to foster a new friend

July 10 marks National Kitten Day, a special day to celebrate all things kittens

Lower Mainland YouTubers claim to be Kelowna display toilet ‘poopers’

RCMP can not speak to legitimacy of video, will be investigating

Haida matriarchs occupy ancient villages as fishing lodges reopen to visitors

‘Daughters of the rivers’ say occupation follows two fishing lodges reopening without Haida consent

RCMP confirm homicide investigation underway near Quesnel

Police releasing few details four days after homicide occurred Monday, July 6

Conservatives say police should be called into investigate WE charity scandal

Trudeau is already under investigation by the ethics commissioner for potential conflict of interest

Most Read