Repair and temporary dam at Mount Polley Mine near Williams Lake.

Mount Polley design, steep additions led to failure

Glacial layer in dam base not understood, plans to buttress slope put off until weight of water and tailings caused breach

The Mount Polley mine dam failed because of an overlooked glacial material layer in the foundation and a series of steep additions that eventually overcame it, an independent engineering review has concluded.

“Basically the weight of the dam was too much for the weak materials in the foundation to bear,” said U.S. consulting engineer Steven Vick, one of three experts called in to examine the failure that caused the dam to breach and fail in August 2014.

The report concludes that the concrete-like glacial till material in the base of the dam wasn’t understood in enough detail when the dam was designed and built in 1997. Later raising of the dam to hold more water and tailings weakened the base layer and led to the failure.

Vick said the additions to the dam were built at a steeper slope than the original dam, and plans to buttress the area were delayed until it was too late.

Energy and Mines Minister Bill Bennett said the report shows there were no warning signs, and no surface inspections could have detected the problem that was overlooked in the design and original construction.

Two more investigations of the mine failure are pending. Bennett said the Chief Inspector of Mines is likely to release his report by June, and the Conservation Officers’ Service will also report when its investigation is complete.

Bennett said the government is willing to see the Mount Polley mine reopen, but the other investigations must be complete first. The parent company Imperial Metals has applied to use an existing pit to store tailings and resume operations without using the original tailings pond again.

 

Just Posted

B.C. BUDGET: Surplus $374 million after bailouts of BC Hydro, ICBC

Growth projected stronger in 2020, Finance Minister Carole James says

Vanderhoof eligible for up to $6M in provincial infrastructure funding

The Northern Capital and Planning Grant will go to four regional districts and 22 municipalities

Province announces $100-million grant funding for Northwest communities

The Northern Capital and Planning Grant will go to four regional districts and 22 municipalities

Prince Rupert Gas Transmission project searches for partners

TransCanada is renewing permits for its natural gas pipeline project to North Coast.

Over 2,000 people used the pool in the first 2-weeks

Lifeguard training course needs a minimum of six people to register before Feb. 21

Peter Tork, Monkees’ lovable bass-guitar player, dies at 77

Tork, Micky Dolenz, David Jones and Michael Nesmith formed the made-for-television rock band

From a drunk judge to Clifford Olson: George Garrett recounts a life in B.C. news radio

New book from ‘Intrepid Reporter’ George Garrett offers readers a glimpse behind the headlines

Wife remembers B.C. man killed in possible case of mistaken identity

Rex Gill was in Kamloops working to support his family after oilfield job dried up

New report calls for regulated heroin sales to curb B.C.’s overdose problem

B.C. Centre on Substance Use points to organized crime and money-laundering as contributing factors

Millennial men least likely to have a family doctor: Statistics Canada

Report found more women have primary care physicians, compared with men

70% of Canadians agree with mandatory vaccines for children: poll

The debate for pro and anti vaccinations has heated up after a measles outbreak in Vancouver

VIDEO: Woman, off-duty cop in serious condition after stabbing outside B.C. elementary school

The officer was interceding in an alleged assault when he and the woman were stabbed

Most Read